Re: MRP Run based on valuation type

$
0
0

Dear,

 

Its not possible to run the MRP based on valuation type.Valuation type functionality is to differentiate valuated stock of same material separately in a plant.It is not the parameter to be considered for MRP.

 

When it comes to MRP, you can have user exit to run the MRP. For example based on Material Type/Material group/MRP type/MRP controller etc...

 

SPRO Settings :

 

 

Regards,

pardhu